All project components are progressing well: The FPSO has been brought back to port after Typhoon Muifa and testing of its facilities is well underway, the conversion of the Gimi FLNG in Singapore, the Hub Terminal on the Mauritania-Senegal maritime border about 10 km offshore, the construction and installation of subsea equipment and the drilling of the first four production wells.
As of this date, the overall implementation rate of the GTA Phase 1 project is now over 87%.